Cannot parent tasklist when creating a task

agentc - January 30, 2007 - 00:03
Project:Tasklist Advanced
Version:HEAD
Component:Code
Category:bug report
Priority:normal
Assigned:Unassigned
Status:postponed (maintainer needs more info)
Description

After installation of Tasklist advanced in 4.7, I cannot create sub tasks. The parent tasklist field is always set to "--MASTER TASKLIST--"

#1

moonray - January 30, 2007 - 16:52

You need to mark the task as a project. Only projects are allowed "subtasks."
An action by definition is a single step. :-)

#2

moonray - January 30, 2007 - 16:53
Status:active» postponed (maintainer needs more info)

Let me know if that solved things, or if there's a real bug in the system.

#3

agentc - January 31, 2007 - 02:15

Yep. This worked I can see the sub task created, but the "Parent Tasklist:" field" is definitely missleading!

#4

moonray - April 3, 2008 - 18:35
Version:4.7.x-1.x-dev» HEAD

Any suggestions on how to make the "Parent Tasklist" field less misleading?

 
 

Drupal is a registered trademark of Dries Buytaert.