Cron job fails after installing latest date calender token modules
vitovonantwon - March 13, 2008 - 18:51
| Project: | Token |
| Version: | 5.x-1.10 |
| Component: | Code |
| Category: | bug report |
| Priority: | normal |
| Assigned: | Unassigned |
| Status: | closed |
Jump to:
Description
Fatal error: Cannot redeclare date_token_list() (previously declared in /home/pojack1/public_html/nyclightwave/modules/date/date/date.module:361) in /home/pojack1/public_html/nyclightwave/modules/token/token_cck.inc on line 226
Any ideas?
I installed the date module, ran update, calander 2.0, ran update, then token, ran update.
Didn't notice the problem until I went to status page and ran the cron job.
Any ideas.
Thanks antonio

#1
You need a later version of Token. See http://drupal.org/node/206649.
#2
Thanks. This worked.
#3
Automatically closed -- issue fixed for two weeks with no activity.