Issue Summary

The first node I made repeat weekly went just fine, but any other event that repeats weekly behaves oddly.

I create the first event, say Friday night. It appears fine in the calender. I make it to repeat weekly. The following event appears on Thursday instead of Friday, and the rest of the events are all Thursday.

It is so puzzling how come the first one went fine but none other. Any help would be appreciated.

Comments

#1

Project:Event» Event Repeat
Version:5.x-1.0» 5.x-1.0

moving to correct project

#2

I'm having the same problem, all the repeated days are one day early when choosing days of the week. Could the code not account for the option to start the day of the week on Sunday or Monday?

#3

Version:5.x-1.0» 5.x-1.1

same problem for me. if you have found a valid solution please post it here.
ciao

#4

I was able to work around this by changing events to use the sitewide timezone, in the event settings.

#5

I already use the sitewide timezones and still have this problem for certain days. Just updated to a more recent version and will test again.

#6

Version:5.x-1.1» master

Moving this issue to head. Looks to be part of an ongoing an issue of problems related to how the dates are decided.

Thanks
Robert

#7

Does this exist in the 2.0 stream of the module?

#8

The issue is related to timezone handling. From what I can tell if you are before GMT it seems to work fine After GMT it doesn't.

Thanks
Robert

#9

subscribing

#10

I had the same problem, but http://drupal.org/node/247663 helped me.

#11

It's happening to me too. First event goes in fine, but next occurance is in 6 days. After that, they repeat every 7 days, thus making them all one day early.